The difference between the actual labor rate multiplied by the actual labor hours worked and the…


Question Description:

33

The difference between the actual labor rate multiplied by the actual labor hours worked and the standard labor rate multiplied by the standard labor hours is the: total labor variance. labor price variance. labor quantity variance. labor efficiency variance.

Answer

33